3395 |
16.4.1 The rigid cover plate shall be adopted for fixation and protection of the portal whose side length or diameter is 20cm~40cm, the steel pipe scaffold shall be erected for the portal whose side length or diameter is 40cm~150cm, and the dense mesh safety network protection and guardrail shall be erected for the portal whose side length or diameter is above 150cm. |
16.4.1 边长或直径为20cm~40cm的洞口应采用刚性盖板固定防护;边长或直径为40cm~150cm的洞口应架设钢管脚手架、满铺脚手板等;边长或直径在150cm以上的洞口应张设密目安全网防护并加护栏。 |
3396 |
16.4.2 After hoisting of the steel beam in building stories, the safety net shall be timely laid zone by zone. |
16.4.2 建筑物楼层钢梁吊装完毕后,应及时分区铺设安全网。 |
3397 |
16.4.2 The inspection of grounding device shall meet the following requirements: |
16.4.2 接地装置检验应符合下列规定: |
3398 |
16.4.2 The inspection results for appearance quality and dimensional error of weld shall meet the requirements of Article 15.5.2 and Article 15.5.5 in this code. |
16.4.2 焊缝的外观质量以及焊缝尺寸偏差的检查结果应符合本规范第15.5.2条及第15.5.5条的规定。 |
3399 |
16.4.3 After hoisting of the steel beam around the story, the guardrail shall be arranged near the edge of each story, and its height shall not be less than 1.2m. |
16.4.3 楼层周边钢梁吊装完成后,应在每层临边设置防护栏,且防护栏高度不应低于1.2m。 |
3400 |
16.4.3 The construction quality of weld ripple and weld bead shall meet the requirements of Article 15.5.6 in this code; After welding, the welding slag and splash shall be cleaned up. |
16.4.3 焊缝的焊波、焊道的施工质量应符合本规范第15.5.6条的要求。焊接完成后,应将焊渣和飞溅物清理干净。 |
3401 |
16.4.3 The specification of grounding wire and its connection with the equipotential grounding terminal board shall be inspected. |
16.4.3 应检查接地线的规格及其与等电位接地端子板的连接。 |
3402 |
16.4.4 The edge scaffolds, operation platforms, and safety nets shall be reliably fixed on the structures during their erection. |
16.4.4 搭设临边脚手架、操作平台、安全挑网等应可靠固定在结构上。 |
3403 |
16.4.4 The installation position, material specification and connection of equipotential grounding terminal board shall be inspected. |
16.4.4 应检查等电位接地端子板安装位置、材料规格和连接。 |
3404 |
16.4.5 The parameter selection, installation position and connecting wire specification of surge protective device shall be inspected. |
16.4.5 应检查浪涌保护器的参数选择、安装位置及连接导线规格。 |