ID 原文 译文
3195 15 Processing schemes and acceptance records of significant projects quality problems; 15 工程的重大质量问题的处理方案和验收记录;
3196 15 Strengthening Steel Members with Enlarged Section 15 钢构件增大截面工程
3197 15 The connection of muff-coupling clamping steel pipe shall meet the following requirements: 15 套接紧定式钢管连接应符合下列规定:
3198 15 The master power input voltage in the machine room shall be measured and when it is confirmed to be normal, it can be tested with power. 15 应测量机房主电源输入电压,确定正常后,方可进行通电测试。
3199 15. Add the key points for lateral load test of single pile and key points for vertical uplift test of single pile. 15.增加单桩水平载荷试验要点,单桩竖向抗拔载荷试验要点。
3200 15. Reference temperature data for nationwide cities and isothermal line map are provided based on the statistics of meteorological observation data of the monthly average maximum and minimum air temperature. 15.根据历年月平均最高和月平均最低气温资料,经统计给出全国各气象台站的基本气温,增加了全国基本气温分布图;
3201 15.1 Construction Preparation 15.1 施工准备
3202 15.1 General Requirements 15.1 一般规定
3203 15.1.1 Technical preparation shall meet the following requirements: 15.1.1 技术准备应符合下列规定:
3204 15.1.1 The inspection of the ATP system functions shall be performed according to the design requirements and relevant technical requirements. 15.1.1 ATP系统功能检验应按设计和相关技术要求进行。