3165 14.6.3 The laser plummet apparatus should be used for the survey of tower verticality (the elevation is above±0.000m) and the diameter of the track circle at the laser point which is drawn by the 360° rotation of the laser apparatus received by the receiving target at 100m elevation shall be less than 10mm. 14.6.3 标高±0.000m以上塔身铅垂度的测设宜使用激光铅垂仪,接收靶在标高100m处收到的激光仪旋转360°划出的激光点轨迹圆直径应小于10mm。
3166 14.6.3 Where fixed roofing is connected with purlin and wallboard is connected with girt, center distance between screws should not be greater than 300mm. 14.6.3 固定式屋面板与檩条连接及墙板与墙梁连接时,螺钉中心距不宜大于300mm。
3167 14.6.4 Continuous sealing rubber strip shall be arranged at lapped joints along longitudinal and transverse direction of roofing. 14.6.4 在屋面板的纵横方向搭接处,应连续设置密封胶条。
3168 14.6.4 The laser plummet apparatus should be arranged at the tower center point when the elevation of the high-rising steel structures is less than 100m, four apparatus should be arranged when the elevation is 100m~200m, and five apparatus (including the tower center point) should be arranged when the elevation is above 200m. 14.6.4 高耸钢结构标高低于100m时,宜在塔身中心点设置铅垂仪;标高为100m~200m时,宜设置四台铅垂仪;标高为200m以上时,宜设置包括塔身中心点在内的五台铅垂仪。
3169 14.6.5 The flashing plate or wrap-edge-plate with favorable sealing performance and appearance shall be arranged around angle section, roof ridge, cornice, roofing opening or protrusion. 14.6.5 在角部、屋脊、檐口、屋面板孔口或突出物周围,应设置具有良好密封性能和外观的泛水板或包边板。
3170 14.6.5 The permissible error for survey with the laser plummet apparatus transferred to the receiving target shall meet those specified in Table 14. 6. 14.6.5 激光铅垂仪投测到接收靶的测量允许误差应符合表14.6.5的要求。
3171 14.6.6 During erection of profiled steel roof, effective measures shall be taken to distribute construction load to relatively large area to prevent roofing from local buckling due to construction concentrated load. 14.6.6 安装压型钢板屋面时,应采取有效措施将施工荷载分布至较大面积,防止因施工集中荷载造成屋面板局部压屈。
3172 14.6.6 When the construction of the high-rising steel structures reaches 100m high, the sunlight deformation observation should be carried out; in addition, the sunlight deformation curve is drawn and the minimum sunlight deformation range is listed. 14.6.6 高耸钢结构施工到100m高度时,宜进行日照变形观测,并绘制出日照变形曲线,列出最小日照变形区间。
3173 14.6.7 During construction on roof, safety measures such as safety rope shall be adopted, and safety net shall also be adopted where necessary. 14.6.7 在屋面上施工时,应采用安全绳等安全措施,必要时应采用安全网。
3174 14.6.7 Round-trip survey along the tower direction should be carried out to determine the elevation of the high-rising steel structures with a steel ruler; the survey results should be corrected with regard to ruler length, temperature & tension and their precision shall be greater than 1/10000. 14.6.7 高耸钢结构标高的测定,宜用钢尺沿塔身铅垂方向往返测量,并宜对测量结果进行尺长、温度和拉力修正,精度应高于1/10000。